Activity and interventions

 

  • Mechanical engineering
  • Procurement


Technical environment

 

  • Business suite
  • Standards
  • CAO

 


Key figures

 

  • Number of project members: 22
  • Project duration: 2 years

Context

The project consisted of the project management of the engineering, procurement and construction of a new calcium ammonium nitrate production unit in an existing complex in South Africa.


 

 

 

ALTEN's achievements

.

The following tasks were performed:

 

Procurement:

  • Tendering.
  • Clarifications/negotiation.
  • Placement of Purchase Orders.
  • Expediting.

 

Mechanical engineering

  • Definition of the equipment.
  • Technical bid evaluations.
  • Technical comparisons.
  • Recommendations.
  • Lay out equipment checks.

 

 

 

ALTEN's Added value

 

  • Flexibility in terms of priority changes.
  • Expertise in technical features.